BP101357 - 6631 Island Highway N (Woodgrove Mall Expansion) -- Drawings Scanned/Attached
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP101357 - 6631 Island Highway N (Woodgrove Mall Expansion) -- Drawings Scanned/Attached | |
---|---|
Neighbourhood: | Dover |
Street Address: | 6631 Island Highway N (Woodgrove Mall Expansion) -- Drawings Scanned/Attached |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP101357 |
Date Application Submitted: | February 17, 1999 |
Application Description: |
21287.4 sq. m. ADDITION with 431 sq.m. mezzanine to existing 43,531.8 sq. m. WOODGROVE MALL. Sprinklered, non-combustible construction. 3.2.2.20 (A1 occup); 3.2.2.24 (A2 occup); and 3.2.2.57 (E occup) 1998 BC Building Code applies. 2 hour FRR floors and supporting structure; 1 hour FRR mezzanine and supporting structure. See BP 101181 for foundation. |
Application Status: | COMPLETED |
Permit Value: | $25,500,000.00 |
Builder: | P C L CONSTRUCTORS PACIFIC INC |
Issued Date: | April 22, 1999 |
File Close Date: | April 03, 2000 |
Process Steps
Task | Status |
---|---|
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
CANCELLED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
CANCELLED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
OCCUPANCY-OLD | PARTIAL |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | PARTIAL |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | PARTIAL |
OCCUPANCY-OLD | PARTIAL |
OCCUPANCY-OLD | PARTIAL |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2000-04-03 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.