BP113033 - 1791 Rajeena Way
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP113033 - 1791 Rajeena Way | |
---|---|
Neighbourhood: | Chase River |
Street Address: | 1791 Rajeena Way |
Type of Application: | Single / Two Family Dwelling |
File Number: | BP113033 |
Date Application Submitted: | June 17, 2008 |
Application Description: |
Construct an on slab two storey single family dwelling with a partially unfinished basement and an attached double garage. REVISION September 30, 2008 Complete the finishing in the basement to include a legal secondary suite of 635 sqft in size. MLB |
Application Status: | COMPLETED |
Permit Value: | $238,317.00 |
Building Area: |
162.39 M2 1,747.95 ft2 |
Issued Date: | July 08, 2008 |
File Close Date: | January 07, 2009 |
Associated Properties
Address | Zone | More |
---|---|---|
1791 RAJEENA WAY | R10 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2009-01-07 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.