BP113460 - 50 Mill Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP113460 - 50 Mill Street | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 50 Mill Street |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP113460 |
Date Application Submitted: | June 23, 2008 |
Application Description: |
Two Part 9 buildings, sprinklered , 3 Storey Townhouses. 1 Hour FRR/FS (party wall) between the townhouse units that is continuous to the underside of the roof sheathing. 1 hr. FRR/FS for the mech. elect rooms. Combustible Construction INSPECTIONS ONLY for blk B Blk B = 50 Mill Street = Part 9, Building area = 1056.3 m2, 7 - Townhouses. Unit 107 - Gar. 28.5 m2- Flr area - 150.9 m2 Unit 108 - Gar. 28.5 m2- Flr area - 150.9 m2 Unit 109 - Gar. 28.5 m2- Flr area - 150.9 m2 Unit 110 - Gar. 28.5 m2- Flr area - 150.9 m2 Unit 111 - Gar. 28.5 m2- Flr area - 150.9 m2 Unit 112 - Gar. 28.5 m2- Flr area - 150.9 m2 Unit 114 - Gar. 28.5 m2- Flr area - 150.9 m2 |
Application Status: | COMPLETED |
Builder: | MTP DEVELOPMENTS (RIMINI) INC |
Issued Date: | November 13, 2008 |
File Close Date: | May 25, 2010 |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
CANCELLED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2010-05-25 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.