BP113931 - 850 Jackson
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP113931 - 850 Jackson | |
---|---|
Neighbourhood: | Duke Point |
Street Address: | 850 Jackson |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP113931 |
Date Application Submitted: | April 27, 2009 |
Application Description: |
Van Isle Barge, Office modular unit , 46 m2, (10 feet x 50 feet) , sprinklered under this permit, Group D, One universal washroom. Accessible ramp to entrance. Letter for the structural integrity of the modular unit. Servicing to unit. Xreference ENG00928- on - off site servicing. |
Application Status: | COMPLETED |
Permit Value: | $15,000.00 |
Builder: | MINHAS GUR |
Issued Date: | August 12, 2009 |
File Close Date: | March 30, 2010 |
Associated Properties
Address | Zone | More |
---|---|---|
850 JACKSON ROAD | I4 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2010-03-30 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.