BP114952 - 617 Hillcrest Ave

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP114952 - 617 Hillcrest Ave
Neighbourhood: Harewood    
Street Address: 617 Hillcrest Ave
Type of Application: Garage / Carport Permit
File Number: BP114952
Date Application Submitted: March 15, 2010
Application Description: Rebuild existing garage, 5 x 10 deck addition

Revision completed: 09-08-10 KM
Added stairs to deck.
2'8" x 6'8" door to garage.
Added parapet wall.
5'-6" x 12'-6" addition to north side.
2'0" x 2'6" window.
permit renewed 03.14.2012
Application Status: COMPLETED
Permit Value: $15,000.00
Issued Date: March 16, 2010
File Close Date: November 05, 2013
Expiry Date: March 14, 2014

Associated Properties

Address Zone More
617 HILLCREST AVENUE R5 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
FRAMING

Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
FINAL-OLD

Final Approval as per requested on plans.

PASSED

2013-11-05

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy