BP116943 - 3225 Emerald Drive
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP116943 - 3225 Emerald Drive | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 3225 Emerald Drive |
Type of Application: | Single / Two Family Alteration |
File Number: | BP116943 |
Date Application Submitted: | February 03, 2012 |
Application Description: | To convert garage into Master Bedroom with ensuite |
Application Status: | RETIRED |
Permit Value: | $12,000.00 |
Builder: | VITRUVIAN CONTRACTING |
Issued Date: | February 17, 2012 |
File Close Date: | May 03, 2016 |
Expiry Date: | February 17, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
3225 EMERALD DRIVE | R5 | Property Report |
Process Steps
Task | Status |
---|---|
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
COMPLETED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
FAILED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.