BP117041 - 1815 Bowen Road -- Scanned
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP117041 - 1815 Bowen Road -- Scanned | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 1815 Bowen Road -- Scanned |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP117041 |
Date Application Submitted: | March 08, 2012 |
Application Description: |
To construct a one storey fitness centre building on this site (VI Fitness Centres for women) Group A2 Occupancy Part 3 building 3.2.2.27 combustible or non-combustible construction - roof unrated one storey 895 square meters building area sprinklered with fire alarm system. No washroom facilities have been provided for males in this womens only facility. Any inclusion of males in this facility will require alterations to the building to provide the appropriate washroom facilities. |
Application Status: | COMPLETED |
Permit Value: | $800,000.00 |
Builder: | WINDLEY CONTRACTING (2010) LTD |
Issued Date: | May 24, 2012 |
File Close Date: | December 10, 2012 |
Associated Properties
Address | Zone | More |
---|---|---|
1815 BOWEN ROAD | COR3 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2012-12-10 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.