BP119239 - 1 1533 Estevan Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP119239 - 1 1533 Estevan Road | |
---|---|
Neighbourhood: | Newcastle/Brechin |
Street Address: | 1 1533 Estevan Road |
Type of Application: | Leasehold Improvements |
File Number: | BP119239 |
Date Application Submitted: | December 12, 2013 |
Application Description: |
Sea Drift Market - Existing Group E - 116.5 m2, reconfiguration of fixtures to create an universal washroom , new mop sink, relocate HWT, new 2 handfree sink , adding interior partition walls . adding grease trap under triple sink , adding 45 min FRR - for roof ; Repair any breaches in the existing demising walls between suites . New finishes. Providing a 1 hour FRR/FS around Electricial room. Ensure electrical room door has a 45min FPR rating (ULc labelled) and self closing device. Existing 1957 building, combustible, unsprinklered, 2815.2m2 building with partial Firewall (non-conforming) between West units (1212.46m2) and remainder of building; centre area (669.5m2) now divided from 933.24m2 East side by 2 hr Firewall (created under equivalency).see permit 108185 |
Application Status: | COMPLETED |
Permit Value: | $60,000.00 |
Building Area: |
116.50 M2 1,253.99 ft2 |
Builder: | TECTONICA MANAGEMENT INC |
Issued Date: | January 17, 2014 |
File Close Date: | July 17, 2014 |
Expiry Date: | January 18, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
1533 ESTEVAN ROAD | CC3 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final Approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final Approval as per requirements on plans. |
PASSED
2014-07-17 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.