BP119372 - 3304 Shearwater Drive
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP119372 - 3304 Shearwater Drive | |
---|---|
Neighbourhood: | Hammond Bay |
Street Address: | 3304 Shearwater Drive |
Type of Application: | Accessory Building |
File Number: | BP119372 |
Date Application Submitted: | January 27, 2014 |
Application Description: |
Accessory building with 2 pc. Bathroom. Revision: May 16, 2014-- Delete double doors on accessory building. Revision 2: June 20, 2014-- Relocate 2 pc. powder room, man door and add window. |
Application Status: | COMPLETED |
Permit Value: | $23,056.39 |
Building Area: |
31.22 M2 336.05 ft2 |
Issued Date: | March 17, 2014 |
File Close Date: | January 06, 2015 |
Expiry Date: | March 16, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
3304 SHEARWATER DRIVE | R5 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite. |
FAILED |
FOOTING/FORMS
Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection. |
FAILED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection. |
FAILED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2015-01-06 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.