Type of Application: | Leasehold Improvements |
File Number: | BP119920 |
Date Application Submitted: | June 30, 2014 |
Application Description: |
Unit 201- Medical Office, Complete and occupy - Accessible - 301.12 m2 - Installing 15 rooms each with sinks , lunch/staff room with sink and 2 washrooms plus one washroom with shower), Universal washroom common in public corridor on main floor. Dropping sprinkler heads into new Tbar ceiling. Existing O hr. FS/FRR between Group D suites, 0 hr. FS/FRR public corridors, 45 min. FRR/FS for exits at each end of public corridor. Building Classification from BP116583 - 750 M2 two story combustible building. sprinklered Classification Group D (3.2.2.56) and Group E (3.2.2.62) 2006 BCBC. 45 min FRR/FS for floor and 45 min FRRsupporting elements. |
Application Status: | COMPLETED |
Permit Value: | $258,000.00 |
Building Area: |
301.12 M2 3,241.23 ft2 |
Builder: | AFX CONSTRUCTION LTD |
Issued Date: | July 18, 2014 |
File Close Date: | October 16, 2014 |
Expiry Date: | July 18, 2016 |
Associated Properties
Address | Zone | More |
---|---|---|
1450 WADDINGTON ROAD | CC1 | Property Report |
Process Steps
Task | Status |
---|---|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final Approval as per requirements on plans. |
PASSED
2014-10-16 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.