BP121934 - 1314 Island Highway
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP121934 - 1314 Island Highway | |
---|---|
Neighbourhood: | Chase River |
Street Address: | 1314 Island Highway |
Type of Application: | Single / Two Family Alteration |
File Number: | BP121934 |
Date Application Submitted: | April 28, 2016 |
Application Description: |
Rot repair. Re insulate and Drywall throughout. Structural engineer of record. J.S. Valliere One storey SFD Habitable space in crawlspace not permitted. REVISION: complete change to interior layout 11.06.2018 |
Application Status: | COMPLETED |
Permit Value: | $5,000.00 |
Builder: | GURDEV HOLDINGS LTD |
Issued Date: | December 28, 2016 |
File Close Date: | March 08, 2019 |
Expiry Date: | December 28, 2018 |
Associated Properties
Address | Zone | More |
---|---|---|
1314 ISLAND HIGHWAY S | COR2 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
FAILED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
FAILED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2019-03-08 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.