BP122384 - 6580 Island Hwy
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP122384 - 6580 Island Hwy | |
---|---|
Neighbourhood: | Dover |
Street Address: | 6580 Island Hwy |
Type of Application: | Leasehold Improvements |
File Number: | BP122384 |
Date Application Submitted: | August 30, 2016 |
Application Description: |
Tenant Improvement (Lordco) - expand retail area, combine two CRU's into one and change of use from E to F2 storage. New retail area to be 779.82m2, new storage area to be 1373.79m2. No FS required between E & F2, two existing accessible washrooms adequate. Occupant load of 259 persons includes retail area 210 persons and storage area 49 persons. Work also includes the installation of 7 new sprinkler heads. Building classified as 3.2.2.67 group E and 3.2.2.77 group F2, non-combustible, sprinklered. REVISION Dec 14 - Install partition wall in retail/parts area, also remove stairs to mezzanine which will no longer be used. |
Application Status: | COMPLETED |
Permit Value: | $80,000.00 |
Builder: | LORDCO AUTO PARTS LTD |
Builder: | ATTN: KIM MAZUR |
Issued Date: | September 29, 2016 |
File Close Date: | February 24, 2017 |
Expiry Date: | October 01, 2018 |
Associated Properties
Address | Zone | More |
---|---|---|
6580 ISLAND HIGHWAY N | CC4 | Property Report |
Process Steps
Task | Status |
---|---|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
FAILED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
FINAL-OLD
Final Approval as per requirements on plans. |
PASSED
2017-02-24 |
FINAL-OLD
Final Approval as per requirements on plans. |
SCHEDULED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.