BP122989 - 369 Milton Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP122989 - 369 Milton Street | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 369 Milton Street |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP122989 |
Date Application Submitted: | March 01, 2017 |
Application Description: |
Adding Two storey - 22 ft. x 24 ft. addition on to the existing carriage house Lower floor = New 532 sq.ft., Existing storage area 236 sq.ft., existing crawl space, Upper floor = New 532 sq.ft, Existing 497 sq.ft, Removing 66 sq.ft. = 1731 sq ft. Ensure no windows in wall closest to the property line. Sprinklered by bylaw. 45 min FRR for the wall closest to the property line , West. , Non perforated soffit West. REVISION: May 12, 2020 - Revise Structural and change layout. REV. July 2-2020- Move Laundry REVISION: MAY 19/21 - Add 3040 window & move BWP to accommodate new window, reduce deck size. |
Application Status: | RETIRED |
Permit Value: | $85,000.00 |
Issued Date: | June 23, 2017 |
File Close Date: | November 05, 2021 |
Expiry Date: | June 23, 2021 |
Associated Properties
Address | Zone | More |
---|---|---|
371 MILTON STREET | R14 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
FAILED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
FAILED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
FAILED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
FAILED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
CANCELLED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
FAILED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
FAILED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
MONITORED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.