BP123046 - 11- 4376 Boban
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP123046 - 11- 4376 Boban | |
---|---|
Neighbourhood: | Pleasant Valley |
Street Address: | 11- 4376 Boban |
Type of Application: | Leasehold Improvements |
File Number: | BP123046 |
Date Application Submitted: | March 17, 2017 |
Application Description: |
(Phillips Brewing - storage/distribution) Revise CRU size within building foot print, revise location and install new demising walls, revise exiting, create new office area, new accessible washroom and new laundry sink. 2,608.63m2 F-2 unsprinklered, combustible one storey building. non-conforming under the 2006 BC Building Code. MAY 10, 2017 - Revised location of accessible washroom. June 13, 17 - Change rear exit vestibule. |
Application Status: | COMPLETED |
Permit Value: | $15,000.00 |
Builder: | FIELD INVESTMENTS |
Issued Date: | May 01, 2017 |
File Close Date: | June 23, 2017 |
Expiry Date: | May 01, 2019 |
Associated Properties
Address | Zone | More |
---|---|---|
4376 BOBAN DRIVE | I2 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
FAILED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final Approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final Approval as per requirements on plans. |
PASSED
2017-06-23 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.