BP123176 - 1900 Boxwood Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP123176 - 1900 Boxwood Road | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 1900 Boxwood Road |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP123176 |
Date Application Submitted: | April 20, 2017 |
Application Description: |
(Lewkowich Engineering) Construction of a new two storey office building. Main floor 457.9m2, Second floor 267.93m2, total building area of 725.83m2. Building classified 3.2.2.61 Group D, up to 2 storeys, and 3.2.2.84 Group F3, sprinklered, with fire alarm system, 45 min FS/FRR exit stairs and 45 min FS/FRR floor assemblies. An alternative solution for construction of exposing building faces (South Wall) to construct a required 1hr FRR non-combustible wall assembly with combustible materials protected by Type 'X' fire rated drywall on the interior and exterior. The alternative solution report also clarifies the Group F3 occupancy laboratory use by calculations of combustible content. REVISION June 20 - All new drawings submitted with revisions to match the issued for construction set REVISION: April 23/18 - Revise sprinkler drawings and change Civil Engineer. |
Application Status: | COMPLETED |
Permit Value: | $1,500,000.00 |
Builder: | TECTONICA MANAGEMENT INC |
Issued Date: | June 09, 2017 |
File Close Date: | June 27, 2018 |
Expiry Date: | June 09, 2019 |
Associated Properties
Address | Zone | More |
---|---|---|
1900 BOXWOOD ROAD | I2 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
FAILED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
CANCELLED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
CANCELLED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
APPROVAL-FIRE-OLD
Approval required prior to Occupancy |
COMPLETED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2018-06-27 |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.