BP124169 - 858 Georgia Avenue (Residential Apartment)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP124169 - 858 Georgia Avenue (Residential Apartment) | |
---|---|
Neighbourhood: | Harewood |
Street Address: | 858 Georgia Avenue (Residential Apartment) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP124169 |
Date Application Submitted: | February 28, 2018 |
Application Description: | Construction of a 27 unit residential apartment building, 790 m2, 3 storey, Group C 3.2.2.50 & Parking Garage Group F2 3.2.2.82. Total area of all floors, including parking garage is 3206.92 m2. Sprinklered, Fire Alarm system, combustible and/or noncombustible construction. 1 hr. F.R.R., F/S required between suites, suites and corridors/stairwells/elevator shaft and for floor assemblies, load-bearing walls and columns. Parking Garage is required to be separated from the remainder of the building by a 1.5 hrs. F.R.R., F/S. |
Application Status: | COMPLETED |
Permit Value: | $3,631,218.00 |
Builder: | WINDLEY CONTRACTING LTD |
Issued Date: | October 03, 2018 |
File Close Date: | October 13, 2019 |
Expiry Date: | October 03, 2020 |
Associated Properties
Address | Zone | More |
---|---|---|
858 GEORGIA AVENUE | CC2 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
APPROVAL-FIRE-OLD
Approval required prior to Occupancy |
COMPLETED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2019-10-13 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.