BP124596 - 703 Hecate Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP124596 - 703 Hecate Street | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 703 Hecate Street |
Type of Application: | Locate Permit |
File Number: | BP124596 |
Date Application Submitted: | July 03, 2018 |
Application Description: |
Relocate house add secondary suite in basement Relocation of home and renovation to be completed within 12 months of permit issue. Oct 9/18: Revision - change direction of suite entry stairs Dec 13/18: Revision - remove drop ceiling on lower floor REVISION: extend footing/move brace wall panel 14.11.2018 REVISION: kitchen windows/doors replaced, layout changed, Bedroom walls/doors added, addition of bathroom group. Tub replaced 28.01.2019 Oct 11/18: Revision- add geotech |
Application Status: | COMPLETED |
Permit Value: | $100,000.00 |
Building Area: |
97.46 M2 1,049.05 ft2 |
Issued Date: | August 21, 2018 |
File Close Date: | June 20, 2019 |
Expiry Date: | August 21, 2019 |
Associated Properties
Address | Zone | More |
---|---|---|
703 HECATE STREET | R14 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PARTIAL |
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
FOOTING/FORMS
Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of Forms prior to any cement being poured. For Footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For Perimeter Drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For Perimeter Drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concete. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concete. |
PASSED |
SANITARY CONNECTION
Pipe Connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe Connection must be visible for inspection. |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
CANCELLED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
INSULATION
Rough in sprinkler must be complete and visible for inspection. |
CANCELLED |
INSULATION
Rough in sprinkler must be complete and visible for inspection. |
PARTIAL |
INSULATION
Rough in sprinkler must be complete and visible for inspection. |
PASSED |
PAPER/FLASHING/WATERPROOFING
To take place after installation of framing, sheathing, building paper, flashing, and/or weatherproofing of openings and after window installation, but before installation of any siding product or stucco wire. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
To take place after installation of framing, sheathing, building paper, flashing, and/or weatherproofing of openings and after window installation, but before installation of any siding product or stucco wire. |
PARTIAL |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
CANCELLED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
CANCELLED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PARTIAL |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PASSED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.