BP125200 - 2562 Departure Bay Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP125200 - 2562 Departure Bay Road | |
---|---|
Neighbourhood: | Departure Bay |
Street Address: | 2562 Departure Bay Road |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP125200 |
Date Application Submitted: | February 04, 2019 |
Application Description: |
Replacing all deck surfaces and installing new side mounted railings. REVISION: Aug 21/19 - Add Structural Engineer and design detail to scope of project for units 315, 419, 511 & 611. REVISION 2: Oct 7/19 - Add Architect and detail to the scope of the project. REVISION 3: July 20/20 - Add Man Lift, CRP and Plumbing Schedule B and drawings. |
Application Status: | ACTIVE |
Permit Value: | $50,000.00 |
Builder: | DO IT RIGHT PROPERTIES INC |
Issued Date: | June 24, 2019 |
Expiry Date: | June 24, 2023 |
Associated Properties
Address | Zone | More |
---|---|---|
107 2562 DEPARTURE BAY ROAD | R8 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.