BP125590 - 1667 Waddington Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP125590 - 1667 Waddington Road | |
---|---|
Neighbourhood: | Townsite |
Street Address: | 1667 Waddington Road |
Type of Application: | Single / Two Family Dwelling |
File Number: | BP125590 |
Date Application Submitted: | June 11, 2019 |
Application Description: |
Construction of a new single family dwelling as principal use on property. 2020-JAN-30 REVISION: 1st floor: shift bathroom window, mechanical room door moved, tub/shower moved. 2nd floor: bathroom revised, partition change in storage. |
Application Status: | COMPLETED |
Permit Value: | $230,000.00 |
Building Area: |
149.39 M2 1,608.02 ft2 |
Builder: | BOEHM CONSTRUCTION LTD |
Issued Date: | January 06, 2020 |
File Close Date: | August 06, 2020 |
Expiry Date: | January 05, 2022 |
Associated Properties
Address | Zone | More |
---|---|---|
1667 WADDINGTON ROAD | R1 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PARTIAL |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PARTIAL |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
FAILED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
FAILED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
PASSED |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PARTIAL |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PARTIAL |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
FAILED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
FAILED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PARTIAL |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PASSED |
OCCUPANCY-OLD
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
FAILED |
OCCUPANCY
Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish |
PASSED
2020-08-06 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.