BP126078 - 5522 Turner Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP126078 - 5522 Turner Road | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 5522 Turner Road |
Type of Application: | Accessory Building |
File Number: | BP126078 |
Date Application Submitted: | January 09, 2020 |
Application Description: | For the construction of a 16'x16' unheated accessory building on vented crawlspace. |
Application Status: | COMPLETED |
Permit Value: | $18,120.96 |
Building Area: |
23.80 M2 256.18 ft2 |
Issued Date: | January 14, 2020 |
File Close Date: | April 08, 2022 |
Expiry Date: | January 13, 2022 |
Associated Properties
Address | Zone | More |
---|---|---|
5522 TURNER ROAD | R5 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
PASSED
2022-04-08 |
FINAL-OLD
Final approval as per requirements on plans. |
SCHEDULED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.