BP126430 - 981 Maughan Rd
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP126430 - 981 Maughan Rd | |
---|---|
Neighbourhood: | Duke Point |
Street Address: | 981 Maughan Rd |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP126430 |
Date Application Submitted: | July 13, 2020 |
Application Description: |
(Convertus Canada) Addition of 593m2 of Group F2 (processing plant). Work includes removing exterior wall of pre-engineered steel bldg, installation of 4 pre-cast concrete composting tunnels and expansion to treatment system; New Principle Entrance for Fire Department Access; Installation at a new location of the fire alarm annunciator panel; Creation of a new sprinkler room with fireline and domestic water service & meter. Sprinkler work includes removing 72 heads and associated piping and installation of 56 heads and associated piping and relocation of new Siamese connection for fire fighting. Main Floor = (1987.5m2 existing+ 593m2 new= 2580.5m2 total) and enclosed mezzanine = 85.56m2 (mezzanine is 4.27% ). No rating required for the mezzanine floor. Providing accessible toilet room and access from parking for persons with disabilities. Original Building Classification 3.2.2.72. 1987m2 , Group F, Division 2 (Processing Plant and Offices), sprinklered with fire alarm system. |
Application Status: | ACTIVE |
Permit Value: | $4,341,000.00 |
Issued Date: | January 14, 2021 |
Expiry Date: | January 16, 2023 |
Associated Properties
Address | Zone | More |
---|---|---|
981 MAUGHAN ROAD | I4 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
WATER CONNECTION
Pipe Connection must be visible for inspection. |
PARTIAL |
WATER CONNECTION
Pipe Connection must be visible for inspection. |
PARTIAL |
WATER CONNECTION
Pipe Connection must be visible for inspection. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
CANCELLED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
MONITORED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.