BP127167 - 6201 Dunbar Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP127167 - 6201 Dunbar Road | |
---|---|
Neighbourhood: | Pleasant Valley |
Street Address: | 6201 Dunbar Road |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP127167 |
Date Application Submitted: | February 09, 2021 |
Application Description: |
(Pleasant Valley Elementary School) Seismic upgrading and addition to existing sprinkler system including 2 additional heads within 1 of 2 existing sprinkler hydraulic calculated designed area. Remove existing stairwell chair lift and installing passenger lift. Adding 2 additional washrooms and relocating 2 sinks. Existing Building: 1980 BCBC Group A-2, 3.2.2.26, 2 storey, building area 2387.8 m2, sprinklered with fire alarm, 45 min FS/FRR for floors, mezzanines and supports REVISION 2022-JUL-04: Elevator addition and water service upgrade. Total GFA addition 29.55 m2 |
Application Status: | ACTIVE |
Permit Value: | $3,000,000.00 |
Issued Date: | October 14, 2021 |
Expiry Date: | October 14, 2023 |
Associated Properties
Address | Zone | More |
---|---|---|
6201 DUNBAR ROAD | CS1 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
APPROVAL-ENGINEERING
Approval required prior to Occupancy |
APPROVED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.