BP127951 - 231 Hansen Road (Parent 200 Hansen Road) (Community Utility Bldg)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP127951 - 231 Hansen Road (Parent 200 Hansen Road) (Community Utility Bldg) | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 231 Hansen Road (Parent 200 Hansen Road) (Community Utility Bldg) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP127951 |
Date Application Submitted: | December 07, 2021 |
Application Description: |
Unit 231 - New construction of single storey accessory building. Building Classification: BCBC 2018 Part 9, 29.73m2 building area, combustible construction, unsprinklered. Total GFA is 29.73m2. Phase 1 of development is 49 units in 15 buildings, and 1 community utility building. |
Application Status: | ACTIVE |
Permit Value: | $80,000.00 |
Builder: | KSG CONSULTING LTD |
Issued Date: | June 15, 2023 |
Expiry Date: | June 15, 2025 |
Associated Properties
Address | Zone | More |
---|---|---|
200 HANSEN ROAD | , R8 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
FAILED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.