BP128713 - 529 Terminal Avenue (The Station)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP128713 - 529 Terminal Avenue (The Station) | |
---|---|
Neighbourhood: | Newcastle/Brechin |
Street Address: | 529 Terminal Avenue (The Station) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP128713 |
Date Application Submitted: | August 25, 2022 |
Application Description: |
("The Station") New construction of a 6 storey, 69 unit apartment building with an underground parkade as a separate building. Building Classifications: Group C 3.2.2.50, Building area 922.3 m2 with Group F3 3.2.2.88 parking garage, Building area 1624.91 m2, sprinklered with fire alarm system, combustible construction. Key FRR/FS are: 1 Hr/ 50 STC between residential suites, 1 Hr/57 STC between residential and elevator, 1 Hr FRR/FS for public corridor, exits, floor and roof assemblies. Alternative Solutions for Exit exposure protection at north and south exit doors with the use of Water Curtain Sprinklers and for Firewall Continuity to create a separate building for the parking garage with the use of an Article 3.1.10, 2 Hr vertical and partial horizontal Firewall supported with 2 Hr FRR construction. Total GFA 6364.74 m2. 2024-OCT-02 REVISION: Change of Structural Engineer. |
Application Status: | ACTIVE |
Permit Value: | $13,500,000.00 |
Builder: | PARKSHORE PROJECTS LTD |
Issued Date: | December 12, 2024 |
Expiry Date: | December 12, 2026 |
Associated Properties
Address | Zone | More |
---|---|---|
529 TERMINAL AVENUE N | COR2 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
SCHEDULED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
FAILED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
CANCELLED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
CANCELLED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
MONITORED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.