Date Application Submitted: August 17, 2023
Application Description: Two-storey addition on crawlspace including legal secondary suite

2024-APR-17 REVISION: Removed south facing windows upper floor, added skylight above stairwell, layout changes in lower bathroom, changed kitchen layout with added laundry and dishwasher for suite
2024-FEB-23 REVISION: Interior layout change, add crawlspace
Application Status: ACTIVE
Permit Value: $236,544.68
Building Area: 102.87 M2
1,107.28 ft2
Builder: SOUTHPAW HOMES LTD
Issued Date: December 13, 2023
Expiry Date: December 13, 2025

Associated Properties

Address Zone More
2340 HIGHLAND BOULEVARD COR1 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

FAILED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
ROUGH IN PLUMBING

Rough In plumbing must be complete including water piping.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

CANCELLED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
FRAMING

Rough in plumbing & electrical must be complete.

FAILED
FRAMING

Rough in plumbing & electrical must be complete.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PASSED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PASSED
FINAL

Final approval as per requirements on plans.

FAILED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy