BP129520 - 420 Albert Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP129520 - 420 Albert Street | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 420 Albert Street |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP129520 |
Date Application Submitted: | November 30, 2023 |
Application Description: |
Change of use from 1 Storey Group D office building to 23 unit Part 9 Group C (residential micro units). Building area: 538.2 m2. Scope of work includes: Seismic upgrade, install sprinkler system, connection to new 4" fire/domestic water service, fire alarm system and full mechanical system. Removal of 10 plumbing fixtures and installation of 115 new fixtures. Key FRR/FS are: 1 Hr/51 STC between units and between units and corridor. Total GFA 636.19 m2. Existing Building Classification: Part 9, one storey Group D(Office Bldg), 538.2m2. combustible construction, unsprinklered, no fire alarm. 2024-MAY-23 REVISION: Add Electrical Engineer for design changes and field review, relocate water entry room to lobby area, increase size for basement electrical room. |
Application Status: | ACTIVE |
Permit Value: | $847,028.00 |
Issued Date: | February 08, 2024 |
Expiry Date: | February 08, 2026 |
Associated Properties
Address | Zone | More |
---|---|---|
420 ALBERT STREET | DT7 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
WATER CONNECTION
Pipe Connection must be visible for inspection. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.