BP129648 - 606 Rotayo Road

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP129648 - 606 Rotayo Road
Neighbourhood: Harewood    
Street Address: 606 Rotayo Road
Type of Application: Single / Two Family Dwelling
File Number: BP129648
Date Application Submitted: January 09, 2024
Application Description: New construction of single-family dwelling with secondary suite

2024-MAY-08 REVISION: Changes to lower floor including window and door locations, updated suite size and layout, and office/bathroom layout in main dwelling with the deletion of the bar sink in the media room.

2025-JAN-29 REVISION: Relocate suite access door, and kitchen sink
Application Status: ACTIVE
Permit Value: $512,068.24
Building Area: 276.85 M2
2,979.99 ft2
Builder: M & S SIDHU CONSTRUCTION NANAIMO LTD
Issued Date: April 04, 2024
Expiry Date: April 04, 2026

Associated Properties

Address Zone More
606 ROTAYO ROAD R5 Property Report

Process Steps

Task Status
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

FAILED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

FAILED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

CANCELLED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PARTIAL
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
WATER CONNECTION

Pipe and Connection must be visable for inspection

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PARTIAL
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.