BP129670 - 990 Brechin Road

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP129670 - 990 Brechin Road
Neighbourhood: Newcastle/Brechin    
Street Address: 990 Brechin Road
Type of Application: Garage / Carport Permit
File Number: BP129670
Date Application Submitted: November 08, 2023
Application Description: New detached one-car garage with cistern for storm water

2025-FEB-26 REVISION: Revised rear landing including roof. Front timber pergola replaced with canopy & brackets. Modified window. Updated door design. Modified exterior finish to cedar board on batten. New gutter details.
2024-SEP-05 REVISION: Floor slab height raised. Revised BCLS. Roof pitch revised from 9/12 to 8/12. Window removed. Side window enlarged. Roof framing revised with ridge beam. Revised truss layout. Lateral bracing removed. Bike wash removed.
2024-MAR-13 REVISION: Add Geotechnical Schedule B.
Application Status: ACTIVE
Permit Value: $45,000.00
Building Area: 46.60 M2
501.60 ft2
Builder: MIDDLETON ARCHITECT
Issued Date: February 27, 2024
Expiry Date: February 27, 2026

Associated Properties

Address Zone More
1075 BEACH DRIVE Property Report
990 BRECHIN ROAD Property Report
990 BRECHIN ROAD R5 Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

FAILED
EXCAVATION

Excavation of soil, prior to placing forms.

PASSED
FOOTING/FORMS

Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
FRAMING

Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.