BP129676 - 1034 Park Avenue (House A)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP129676 - 1034 Park Avenue (House A) | |
---|---|
Neighbourhood: | Harewood |
Street Address: | 1034 Park Avenue (House A) |
Type of Application: | Single / Two Family Dwelling |
File Number: | BP129676 |
Date Application Submitted: | November 24, 2023 |
Application Description: |
New construction of single-family dwelling on strata'd duplex lot (House A) Building A (BP129676) GFA is 204.41 m². Building B (BP129677) GFA is 187.85 m². DCC's charged at multi-family rate on Building B for maximum of 170 m² (stair exemption applies). 1 SFD credit applied to Building B. |
Application Status: | ACTIVE |
Permit Value: | $395,877.91 |
Building Area: |
204.41 M2 2,200.25 ft2 |
Builder: | PARKCITY CONSTRUCTION LTD |
Issued Date: | September 04, 2024 |
Expiry Date: | September 04, 2026 |
Associated Properties
Address | Zone | More |
---|---|---|
1034 PARK AVENUE | R5 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PARTIAL |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
PASSED |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PARTIAL |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PARTIAL |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PASSED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.