BP129778 - 123 Nicol Street (Principle Properties)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP129778 - 123 Nicol Street (Principle Properties)
Neighbourhood: South End    
Street Address: 123 Nicol Street (Principle Properties)
Type of Application: Commercial / Multi-Res Alteration
File Number: BP129778
Date Application Submitted: January 09, 2024
Application Description: Permit to resolve CIB06007 "DO NOT OCCUPY ORDER". Double permit fees charged under Building Bylaw 7224 Section 30.7 for commencing work without first obtaining the required building permit
Unit 201 "Change of occupancy" from Group E to Group D. Combine Units 101 & 201 into 1 Group D CRU in a 2 storey building. Scope of work includes cap abandoned upper floor washroom services, addition of one unisex washroom, one universal washroom and kitchen sink on upper floor. Existing lower floor plumbing fixtures to remain. Complete interior partition renovation on both floors, existing exits and service room to remain. Addition of 0.57 m2 storage room at Nicol St frontage. Interior paths of travel and universal washroom to CSA B651-12.
Building Classification: 2018 BCBC Part 9 with Part 4 structure design, building area: 183 m2, two storeys, Group D, combustible and noncombustible construction, unsprinklered, without fire alarm. 45-min FRR floors/walls/columns/arches. No FRR req'd for roof.
Application Status: ACTIVE
Permit Value: $85,000.00
Builder: PARKSHORE PROJECTS LTD
Expiry Date: January 09, 2025

Associated Properties

Address Zone More
123 NICOL STREET DT12 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

FAILED
FOOTING/FORMS

Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy