BP129871 - 2264 Leighton Road

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP129871 - 2264 Leighton Road
Neighbourhood: Westwood    
Street Address: 2264 Leighton Road
Type of Application: Single / Two Family Dwelling
File Number: BP129871
Date Application Submitted: March 12, 2024
Application Description: To construct a new 2-storey single-family dwelling building with a secondary suite slab on grade and attached 2-car garage

2024-OCT-16 REVISION: Delete ensuite tub on main floor, add interior fire-rated door to secondary suite from hallway

2024-JUN-18: REVISION: Add Geotechnical Engineer of Record

2024-NOV-15 REVISION: Change braced wall panels at entrance to columns, adjust braced wall panels to suit site conditions

Application Status: ACTIVE
Permit Value: $651,389.20
Building Area: 358.21 M2
3,855.74 ft2
Issued Date: May 31, 2024
Expiry Date: May 31, 2026

Associated Properties

Address Zone More
2264 LEIGHTON ROAD R5 Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

FAILED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

FAILED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

FAILED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

FAILED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PASSED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

CANCELLED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

PARTIAL
STORM CONNECTION

Pipe and Connection must be visible for inspection

PARTIAL
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PARTIAL
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PARTIAL
WATER CONNECTION

Pipe and Connection must be visable for inspection

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

CANCELLED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

SCHEDULED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

FAILED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

FAILED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy