BP129875 - 2332 Arbot Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP129875 - 2332 Arbot Road | |
---|---|
Neighbourhood: | Westwood |
Street Address: | 2332 Arbot Road |
Type of Application: | Single / Two Family Dwelling |
File Number: | BP129875 |
Date Application Submitted: | April 04, 2024 |
Application Description: |
Substantial reconstruction of a part 9 single family dwelling. Work includes a large addition and converting the existing portion of the home to an attached secondary suite. Step 3 of the Energy Step Code will apply to the entire home. |
Application Status: | ACTIVE |
Permit Value: | $725,000.00 |
Building Area: |
344.38 M2 3,706.87 ft2 |
Builder: | OWEN GARDINER CONSTRUCTION LTD |
Issued Date: | July 25, 2024 |
Expiry Date: | July 25, 2026 |
Associated Properties
Address | Zone | More |
---|---|---|
2332 ARBOT ROAD | R5 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete |
PASSED |
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
FAILED |
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PARTIAL |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
CANCELLED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PARTIAL |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.