BP130160 - 12-4890 Rutherford Road (Fatburger)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP130160 - 12-4890 Rutherford Road (Fatburger) | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 12-4890 Rutherford Road (Fatburger) |
Type of Application: | Leasehold Improvements |
File Number: | BP130160 |
Date Application Submitted: | June 17, 2024 |
Application Description: |
Tenant improvement, existing Group A2, 207 m2, work includes kitchen renovation, adding plumbing fixtures, moving walk-in cooler, adding walk-in freezer Existing 648 m2 unsprinklered building, 2hr FS/FRR between A2 and both adjacent D and E occupancies. Nov 13/24 - Revision: sanitary drainage lines revised REVISION 2025-FEB-13: Add fire suppression systems engineer for kitchen wet chemical system. |
Application Status: | COMPLETED |
Permit Value: | $175,000.00 |
Builder: | MKB VENTURES LTD |
Issued Date: | October 23, 2024 |
File Close Date: | February 14, 2025 |
Expiry Date: | October 23, 2026 |
Associated Properties
Address | Zone | More |
---|---|---|
4890 RUTHERFORD ROAD | COR3 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
CANCELLED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
MONITORED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
CANCELLED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
APPROVAL-VIHA
Approval required prior to Occupancy |
APPROVED |
FINAL
Final Approval as per requirements on plans. |
CANCELLED |
FINAL
Final Approval as per requirements on plans. |
CANCELLED |
FINAL
Final Approval as per requirements on plans. |
FAILED |
FINAL
Final Approval as per requirements on plans. |
CANCELLED |
FINAL
Final Approval as per requirements on plans. |
PASSED
2025-02-14 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.