BP130160 - 12-4890 Rutherford Road (Fatburger)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP130160 - 12-4890 Rutherford Road (Fatburger)
Neighbourhood: Rutherford    
Street Address: 12-4890 Rutherford Road (Fatburger)
Type of Application: Leasehold Improvements
File Number: BP130160
Date Application Submitted: June 17, 2024
Application Description: Tenant improvement, existing Group A2, 207 m2, work includes kitchen renovation, adding plumbing fixtures, moving walk-in cooler, adding walk-in freezer

Existing 648 m2 unsprinklered building, 2hr FS/FRR between A2 and both adjacent D and E occupancies.

Nov 13/24 - Revision: sanitary drainage lines revised
REVISION 2025-FEB-13: Add fire suppression systems engineer for kitchen wet chemical system.
Application Status: COMPLETED
Permit Value: $175,000.00
Builder: MKB VENTURES LTD
Issued Date: October 23, 2024
File Close Date: February 14, 2025
Expiry Date: October 23, 2026

Associated Properties

Address Zone More
4890 RUTHERFORD ROAD COR3 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible.

CANCELLED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visible for inspection.

PASSED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PASSED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

MONITORED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

CANCELLED
PLUMBING FINAL

All fixtures must be in place.

PASSED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
APPROVAL-FIRE

Approval required prior to Occupancy

APPROVED
APPROVAL-VIHA

Approval required prior to Occupancy

APPROVED
FINAL

Final Approval as per requirements on plans.

CANCELLED
FINAL

Final Approval as per requirements on plans.

CANCELLED
FINAL

Final Approval as per requirements on plans.

FAILED
FINAL

Final Approval as per requirements on plans.

CANCELLED
FINAL

Final Approval as per requirements on plans.

PASSED

2025-02-14

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.