BP130246 - 100 Whitefish Place

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP130246 - 100 Whitefish Place
Neighbourhood: Hammond Bay    
Street Address: 100 Whitefish Place
Type of Application: Single / Two Family Dwelling
File Number: BP130246
Date Application Submitted: August 21, 2024
Application Description: New construction of 2 storey single-family dwelling slab on grade with secondary suite

2024-NOV-27 REVISION: Extend length of north east wall, move basement exterior door to north east side of house, kitchen window increased in size, and braced wall panel moved to accommodate kitchen window size change

2024-DEC-11 REVISION: Changed windows in bedroom 5, adjusted braced wall layout to suit

2024-DEC-31 REVISION: Add window in suite living room

2025-MAR-25 REVISION: Change Energy Advisor
Application Status: ACTIVE
Permit Value: $755,920.29
Building Area: 417.22 M2
4,490.91 ft2
Issued Date: October 25, 2024
Expiry Date: October 25, 2026

Associated Properties

Address Zone More
100 WHITEFISH PLACE R10 Property Report

Process Steps

Task Status
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

CANCELLED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

CANCELLED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PASSED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
WATER CONNECTION

Pipe and Connection must be visable for inspection

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

CANCELLED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

CANCELLED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

CANCELLED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

CANCELLED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
APPROVAL-ENGINEERING

Approval required prior to Occupancy

REQUIRED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.